Cesspool Conversion Permit Process for Hawaiʻi Island

By Hawaiʻi Cesspool Help · Published


This is the practical sequence most Hawaiʻi Island homeowners can expect when replacing a cesspool with an approved individual wastewater system. The engineer remains the primary technical contact and determines which steps apply to the property.

Start with the property, not a system product. Site conditions, wastewater flow, setbacks, soils, water sources, existing improvements, and agency requirements drive the design.

1. Confirm the property and system

Collect the TMK, site address, ownership information, known wastewater records, and any cesspool card. Confirm whether the property is sewer-connected or served by an onsite system.

2. Hire a Hawaii-licensed civil engineer

Verify the engineer's license status through DCCA. The engineer evaluates the site, develops the design, and communicates with DOH for IWS approval.

3. Complete site evaluation and design

The engineer documents property conditions, wastewater demand, proposed system type, setbacks, and the disposal area. Additional testing or specialist input may be needed.

4. Submit the IWS application

The engineer assembles the applicable DOH forms, certifications, plans, and supporting documents and submits the application through the state process.

5. Resolve review comments

DOH may approve the plans or return comments. The engineer answers questions and revises the package when necessary. Do not start construction before the required approval.

6. Obtain construction permits and hire contractors

Confirm county building or plumbing permit needs. Verify contractor licenses and use the approved plans when obtaining proposals.

7. Build and document the system

The contractor installs the system. The engineer inspects required work, documents deviations, and prepares the final construction information.

8. Close the old cesspool correctly

Closure and filling must follow the approved design and applicable rules. Keep contractor certification, photos, receipts, and inspection records.

9. Obtain final approval to use

The engineer submits the construction inspection report and required certifications. Keep the final DOH approval and maintenance information with the property records.

Documents commonly involved

Official starting points

Start Your Project


This resource is general information, not engineering, legal, tax, real-estate, or permitting advice. Requirements vary by property. Confirm decisions with the applicable agency and Hawaii-licensed professionals.